Johor new launches, made easy. Shortlists, MM2H and investment in one place.新山新盘,轻松了解。选房、MM2H与投资,一站搞定。

Malaysia Home Finder logo Malaysia Home Finder 新山房产,轻松找对家

RTS Link Johor Bahru–Singapore: The Facts Buyers Need (Oct 2026) | 新山—新加坡RTS捷运:买房前要知道的事实(2026年10月)

· Malaysia Home Finder

RTS Link Johor Bahru–Singapore: The Facts Buyers Need (Oct 2026)

The RTS Link between Bukit Chagar in Johor Bahru and Woodlands North in Singapore is now expected to start passenger service in February 2027. Malaysia’s Ministry of Transport and Singapore’s Land Transport Authority (LTA) said so in a joint statement on 2 October 2026. The earlier target was January 2027. The fare has not been announced yet.连接新山武吉查卡(Bukit Chagar)与新加坡兀兰北(Woodlands North)的RTS捷运,现预计于2027年2月开始载客。马来西亚交通部与新加坡陆路交通管理局(LTA)在2026年10月2日的联合声明中宣布了这一点。原定目标是2027年1月。票价尚未公布。

Last checked: 13 Oct 2026.最后核对:2026年10月13日。

Key facts at a glance关键事实一览

Item项目Fact事实Source来源
Expected start预计通车February 2027, subject to safety certification and approval by both governments2027年2月,须先通过安全认证并获两国政府批准Joint statement, 2 Oct 2026联合声明,2026年10月2日
Fare票价Not announced. To be set and announced jointly by both countries尚未公布,将由两国共同决定并公布Transport Minister Anthony Loke, 18 Aug 2026交通部长陆兆福,2026年8月18日
Journey time车程About 5 minutes between the two stations两站之间约5分钟LTALTA
Length长度About 4 km约4公里LTALTA
Capacity运载量Up to 10,000 passengers per hour in each direction每个方向每小时最多1万人次LTALTA
Stations车站Bukit Chagar (JB) and Woodlands North (Singapore). Depot at Wadi Hana, JB武吉查卡(新山)和兀兰北(新加坡),车厂位于新山Wadi HanaLTALTA
Immigration出入境Both countries’ checks are done at the departure station. No second check on arrival两国检查都在出发站完成,抵达后不必再过关LTALTA
Operator营运商RTS Operations Pte Ltd, a joint venture of Prasarana Malaysia and SMRTRTS Operations Pte Ltd,由马来西亚国家基建公司(Prasarana)与SMRT合资LTALTA
Expected riders预计客流About 40,000 a day when it opens通车时每天约4万人次The Star, 18 Aug 2026; MRT Corp《星报》,2026年8月18日;MRT Corp

Buying as a foreigner?外国买家?

Tell us your budget. We send the projects and units that meet the foreigner minimum.告诉我们预算,我们发给您符合外国人门槛的项目与单位。

Why the date moved为什么延期

The joint statement says the works in both countries are substantially complete. What remains is testing and commissioning. The operator, RTS Operations (RTSO), expects to finish final system tests and trial runs by 31 December 2026. An independent safety assessor must then certify the system. After that, both governments review the certification and approve passenger service.联合声明指出,两国的工程已大致完成,剩下的是测试和调试。营运商RTS Operations(RTSO)预计在2026年12月31日前完成最后的系统测试和试运行。之后须由独立安全评估机构认证,再由两国政府审核认证并批准载客。

So February 2027 is a target, not a fixed opening day. When we checked on 13 Oct 2026, LTA’s project page still said “end of 2026”. We go by the newer joint statement.所以2027年2月是目标,不是确定的通车日。我们在2026年10月13日核对时,LTA项目网页仍写着”2026年底”。我们以较新的联合声明为准。

The fare: what we know票价:目前所知

There is no official fare yet. On 18 August 2026, Transport Minister Anthony Loke said the fare and the opening date would be announced jointly by Malaysia and Singapore, and that neither side would announce alone. Fare figures you may see online are estimates, not official. We will update this page when the fare is published.目前还没有官方票价。交通部长陆兆福在2026年8月18日表示,票价和通车日期将由马新两国共同宣布,任何一方都不会单独公布。网上流传的票价只是估计,不是官方数字。票价公布后我们会更新本页。

What changes for buyers对买家意味着什么

  • Walk-zone homes. Your trip becomes the walk to Bukit Chagar, immigration, then a 5-minute ride. Check the real walking route, not a straight line. Our measured walks are on the Near RTS Bukit Chagar page.步行区住宅:行程变成步行到武吉查卡站、过关,再搭约5分钟的车。请看实际步行路线,不是直线距离。我们实测的步行路线列在RTS武吉查卡附近页面。
  • Homes within 10 km. You still need a car, bus or shuttle to reach Bukit Chagar. The government plans at least 200 new buses from JB housing areas to Bukit Chagar under SBST 2.0, timed for the RTS opening (Bernama, 18 Aug 2026). A developer shuttle is the developer’s own plan, so ask whether it is approved.10公里内的住宅:仍需开车、搭巴士或接驳车到武吉查卡。政府计划在SBST 2.0下增加至少200辆巴士,从新山各住宅区开往武吉查卡,配合RTS通车(马新社,2026年8月18日)。发展商的接驳车是发展商自己的计划,请问清楚是否已获批准。
  • KTM Komuter link. A RM60 million bridge will link the RTS station to the Komuter service. It is expected to take about 12 months to build (Bernama, 18 Aug 2026).KTM电动火车连接:政府将建一座耗资6000万令吉的天桥,连接RTS车站与Komuter电动火车,预计约12个月完成(马新社,2026年8月18日)。
  • The Causeway stays busy. The RTS carries up to 10,000 people an hour each way. Singapore’s land checkpoints cleared more than 598,000 travellers on 19 June 2026 alone (ICA). The RTS takes a share of the crossing. It does not replace the Causeway or the Second Link.长堤依然繁忙:RTS每个方向每小时最多载1万人。新加坡陆路关卡仅在2026年6月19日一天就为超过59.8万名旅客办理通关(ICA)。RTS只分担一部分人流,不会取代长堤或第二通道。
  • More homes near the station. More than 14,000 apartment units are expected to complete in 2029 and 2030 near the RTS corridor, according to industry estimates reported by NST (5 Jan 2026). See our Johor supply guide.车站附近新房增加:据《新海峡时报》(2026年1月5日)引述业界估计,RTS沿线在2029和2030年将有超过1.4万个公寓单位完工。详见我们的柔佛供应指南。

A short checklist before you buy买房前的简单核对清单

  • Ask how the walk was measured. We quote measured walking or road routes. A developer’s figure is shown as “the developer quotes”.问清楚步行距离是怎么量的。我们只引用实测的步行或道路路线;发展商的数字会注明”发展商称”。
  • Ask whether a link bridge or covered walkway is built, approved, or only proposed.问清楚连接天桥或有盖走道是已建好、已获批,还是只是建议。
  • Compare the project’s completion date with the RTS start.比较项目完工日期与RTS通车时间。
  • Check what tenants pay today in completed buildings nearby. See today’s rental market.查看附近已完工大楼现在的租金,见今日租赁市场。
  • Don’t buy on a promised price rise. Nobody can promise one.不要因为别人承诺会涨价而买。没有人能保证涨价。

Start with JB City Centre and the Near RTS list. For example, Summer Suites is about 1.4 km from RTS Bukit Chagar on our measured route. Also see Coronade Twins and R&F Princess Cove Phase 3. Foreigners: Johor’s usual minimum is RM1 million for strata homes, with state consent. See our foreigner guide.可先看新山市中心和RTS附近项目列表。例如Summer Suites按我们实测路线距RTS武吉查卡站约1.4公里。也可看Coronade Twins和富力公主湾第三期。外国人:柔佛一般规定分层地契住宅最低RM1百万,并须获州政府批准。详见外国人购房指南。

FAQ常见问题

When will the RTS Link open?RTS什么时候通车?

The target is February 2027, per the joint statement of 2 Oct 2026. It depends on independent safety certification and approval by both governments, so the date can still move.根据2026年10月2日的联合声明,目标是2027年2月。这取决于独立安全认证和两国政府批准,所以日期仍可能变动。

Ask us this on WhatsApp →在WhatsApp问我们 →

How much is the RTS fare?RTS票价多少?

It has not been announced as of 13 Oct 2026. Malaysia and Singapore will set and announce it together. Treat any figure you see online as unofficial.截至2026年10月13日尚未公布。马新两国将共同决定并宣布。网上看到的数字都不是官方的。

Ask us this on WhatsApp →在WhatsApp问我们 →

How long is the ride?车程多久?

About 5 minutes between Bukit Chagar and Woodlands North (LTA). Add your walk and immigration time at the departure station.武吉查卡到兀兰北约5分钟(LTA)。还要加上步行时间和在出发站过关的时间。

Ask us this on WhatsApp →在WhatsApp问我们 →

Do I clear immigration twice?要过关两次吗?

No. Customs, immigration and quarantine for both countries are at the departure station. You do not clear again on arrival (LTA).不用。两国的关税、移民和检疫都设在出发站,抵达后不必再过关(LTA)。

Ask us this on WhatsApp →在WhatsApp问我们 →

Can the RTS carry everyone who crosses today?RTS能载走现在所有过关的人吗?

No. Its capacity is up to 10,000 passengers an hour each way. Singapore’s land checkpoints handled a record of more than 598,000 travellers on 19 June 2026 (ICA). Buses, cars and the Second Link stay important.不能。RTS每个方向每小时最多1万人次,而新加坡陆路关卡在2026年6月19日创下超过59.8万人次的纪录(ICA)。巴士、汽车和第二通道仍然重要。

Ask us this on WhatsApp →在WhatsApp问我们 →

Will the RTS push up property prices?RTS会让房价上涨吗?

We can’t promise that, and nobody can. Supply near the station is also rising. Buy a home you would use or rent out at today’s rents, which you can check.我们不能保证,也没有人能保证。车站附近的供应也在增加。请以自住或按今天可查证的租金出租为前提来买。

Ask us this on WhatsApp →在WhatsApp问我们 →

Sources资料来源

WhatsApp us for floor plans and price bands.WhatsApp我们,索取户型图和价格范围。

One response to “RTS Link Johor Bahru–Singapore: The Facts Buyers Need (Oct 2026) | 新山—新加坡RTS捷运:买房前要知道的事实(2026年10月)”

  1. […] Passenger service is now expected in February 2027, moved from January under a joint statement by Singapore’s Land Transport Authority and Malaysia’s Ministry of Transport on 2 October 2026. Transport Minister Anthony Loke described February as a buffer rather than a delay. Full detail is in our RTS Link facts page.载客服务目前预计在2027年2月开始,比原定的1月推迟。这是新加坡陆路交通管理局与马来西亚交通部在2026年10月2日联合文告中宣布的。交通部长陆兆福形容2月是缓冲期,而不是延误。完整资料见我们的RTS Link事实页面。 […]

Leave a Reply

Your email address will not be published. Required fields are marked *

Which fit me?哪些适合我?Ask about this就此提问